Athol PS - Shade Structure

Posted by John Jacob at

In the recent school holidays, Mass Energy Australia undertook a PVC shade sail structure as Athol PS. 

This project took 5 days of work (150 man hours) to complete - which was two weeks in total, from the beginning to hand over to school.  We allowed one week for concrete curing before steel went up.

 Access was hard and labour intensive as we had to lay 60m of protection across a sports field surface to ensure protection from all the equipment coming and going to site. This protection had to be removed at the end of every day .

 

Having our own truck to transport steel and equipment, made it easier to complete the project on time and within budget.

Our Client is very happy and we look forward to selling and installing more. 

 

 